Filing Requirements for Municipal Electric Utilities
Municipal electric utilities must file for construction authority if construction
projects exceed a certain cost threshold. These filing requirements
cover the generally small construction projects normally proposed
by municipal electric utilities. These projects are most always
classified as Type III (or less commonly as Type II) projects under
Wis. Admin. Code ch. PSC 4. Projects can include new or expanded
buildings, new or expanded substations, certain transmission and/or
distribution construction or upgrade projects, and small generation
projects. In order to obtain construction authority, an application
must be filed with the Commission by following the appropriate filing requirements. Contact Commission Staff to determine
which portions of the Transmission Line or Power Plant application filing requirements would apply.
|